I am going to be moving the VLAN servicing SLIX and bridging all three
datacenters, C7, XMission, and Level3 tomorrow morning at 3am. Since
this is on a LAG, there should be no interruption.
The Social Hall LAG move is complete. There was no interruption.
I may be moving Delong fiber as well today, if Level3 has done the
cross-connect from Viawest. I'll notify if that is about to happen.
I am moving the Social Hall 20Gb LAG today off Zayo to UTOPIA fiber.
There should be no interruption. This should increase the stability and
reliability of the SLIX Social Hall link, as the Zayo fiber has not been
good.